What are your limitations for building in cold weather and harsh climate conditions?

Our tanks offer factory-manufactured sheets that are assembled on-site which results in minimal limitations due to weather or environment conditions. We have experience building during harsh climates for projects located in northern BC, Alberta, Saskatchewan and Manitoba during the winter months.

When using Flat Panel Tanks with joint sealants, it is important to note that the sealant will not be cured in sub-zero temperatures; generally after erection of the tank in cold temperatures, the tank is hydrotested in the coming spring months; If time is of essence, heating and hoarding has been used to speed up the curing process and commissioning.